− | <br><u></u><u>Definition of the problem</u> | + | == <br><u></u><u>Definition of the problem</u> == |
| | | |
| Stand-alone hydropower schemes are often characterised by high load peaks but low average energy demand. This is particularly the case with community <br>electrification schemes in developing countries where average demand can be as low as 15 to 20% of the peak demand. This has two main disadvantages: | | Stand-alone hydropower schemes are often characterised by high load peaks but low average energy demand. This is particularly the case with community <br>electrification schemes in developing countries where average demand can be as low as 15 to 20% of the peak demand. This has two main disadvantages: |
Line 10: |
Line 10: |
| *During times of low demand, the power from the hydro is only partially utilised and, since most stand-alone schemes are run-of-river, available energy is wasted. This reduces the benefits to the recipients and the overall cost-effectiveness of the scheme. | | *During times of low demand, the power from the hydro is only partially utilised and, since most stand-alone schemes are run-of-river, available energy is wasted. This reduces the benefits to the recipients and the overall cost-effectiveness of the scheme. |
| | | |
− | <u></u><u>Power demand and end use possibilities </u> | + | == <u></u><u>Power demand and end use possibilities </u> == |
| | | |
| The demand for power and end use possibilities should be accessed during the phase of feasibility studies. The primary use of micro-hydropower in the rural context of the country is usually for household lighting. Thus, in order to optimise the use of the micro-hydropower plant (and thus increase its financial viability), the installed capacity should be governed by household demand. The end uses (non -lighting uses) should ideally complement the lighting use. If the end uses are such that they can be operated during the non -lighting hours, the size of the scheme need not be unnecessarily increased. Thus, at any time, the total capacity of end uses under operation should be limited to the installed capacity, which is governed by the lighting demand. However, other approaches to sizing the plant capacity may also be proposed, provided that the financial viability can be demonstrated. | | The demand for power and end use possibilities should be accessed during the phase of feasibility studies. The primary use of micro-hydropower in the rural context of the country is usually for household lighting. Thus, in order to optimise the use of the micro-hydropower plant (and thus increase its financial viability), the installed capacity should be governed by household demand. The end uses (non -lighting uses) should ideally complement the lighting use. If the end uses are such that they can be operated during the non -lighting hours, the size of the scheme need not be unnecessarily increased. Thus, at any time, the total capacity of end uses under operation should be limited to the installed capacity, which is governed by the lighting demand. However, other approaches to sizing the plant capacity may also be proposed, provided that the financial viability can be demonstrated. |
Line 16: |
Line 16: |
| In order to access the power requirements, the number of beneficiary households and the average power demand per household should be determined based on discussions with the community. As mentioned earlier attempts should be made to strike a balance between the technical aspects of the scheme and the demand of the community for electricity. Similarly, the type of end uses, their capacities and exp ected annual operating time based on local resources available and market opportunity should de determined. The prospective entrepreneurs willing to install the various end uses should be identified at the detailed feasibility stage. | | In order to access the power requirements, the number of beneficiary households and the average power demand per household should be determined based on discussions with the community. As mentioned earlier attempts should be made to strike a balance between the technical aspects of the scheme and the demand of the community for electricity. Similarly, the type of end uses, their capacities and exp ected annual operating time based on local resources available and market opportunity should de determined. The prospective entrepreneurs willing to install the various end uses should be identified at the detailed feasibility stage. |
| | | |
− | <u>Forecast and management of load and demand</u> | + | == <u>Forecast and management of load and demand</u> == |
| | | |
| Why demand forecast? | | Why demand forecast? |
Line 30: |
Line 30: |
| *productive use (milling and other agricultural processing, kiosks, welding and carpentry workshops, etc.) | | *productive use (milling and other agricultural processing, kiosks, welding and carpentry workshops, etc.) |
| | | |
− | <br> How to make a forecast: [[Image:How to make a forecast.jpg|thumb|center|How to make a forecast]] | + | == <br> How to make a forecast: [[Image:How to make a forecast.jpg|thumb|center|How to make a forecast]] == |
| | | |
− | Load and demand side management by reducing peaks and/or demand: | + | == Load and demand side management by reducing peaks and/or demand: == |
| | | |
| *sensitising consumers/ awareness raising (e.g. by energy-savign bulbs, promotion of productive end use, etc.) | | *sensitising consumers/ awareness raising (e.g. by energy-savign bulbs, promotion of productive end use, etc.) |
| *creating special tariff system, e.g. combined with installation of current limiters | | *creating special tariff system, e.g. combined with installation of current limiters |
| + | |
| + | <br> |
| + | |
| + | = Load forecast modell = |
| + | |
| + | The Modell was developed in Ethiopia, please check with EnDev Ethioipa (Bart-Jan) if it can be distributed. |
| + | |
| + | <br> |
| | | |
| ---- | | ---- |
| | | |
− | Further reading: [http://www.berr.gov.uk/files/file37656.pdf Improving Efficiency and Accessibility of Micro-Hydro Power Through Intelligent Load Management] (case study from Uganda) | + | Further reading: [http://www.berr.gov.uk/files/file37656.pdf Improving Efficiency and Accessibility of Micro-Hydro Power Through Intelligent Load Management] (case study from Uganda) |
| | | |
| [[Category:Hydro]] | | [[Category:Hydro]] |
Stand-alone hydropower schemes are often characterised by high load peaks but low average energy demand. This is particularly the case with community
electrification schemes in developing countries where average demand can be as low as 15 to 20% of the peak demand. This has two main disadvantages:
The demand for power and end use possibilities should be accessed during the phase of feasibility studies. The primary use of micro-hydropower in the rural context of the country is usually for household lighting. Thus, in order to optimise the use of the micro-hydropower plant (and thus increase its financial viability), the installed capacity should be governed by household demand. The end uses (non -lighting uses) should ideally complement the lighting use. If the end uses are such that they can be operated during the non -lighting hours, the size of the scheme need not be unnecessarily increased. Thus, at any time, the total capacity of end uses under operation should be limited to the installed capacity, which is governed by the lighting demand. However, other approaches to sizing the plant capacity may also be proposed, provided that the financial viability can be demonstrated.
In order to access the power requirements, the number of beneficiary households and the average power demand per household should be determined based on discussions with the community. As mentioned earlier attempts should be made to strike a balance between the technical aspects of the scheme and the demand of the community for electricity. Similarly, the type of end uses, their capacities and exp ected annual operating time based on local resources available and market opportunity should de determined. The prospective entrepreneurs willing to install the various end uses should be identified at the detailed feasibility stage.
The Modell was developed in Ethiopia, please check with EnDev Ethioipa (Bart-Jan) if it can be distributed.