− | [[File:IrradianceTest.jpg|thumb|right|300px|Measuring the irradiance during the Site Acceptance Test (Source: Reinhold Schmidt)]] | + | [[File:IrradianceTest.jpg|thumb|right|300px|Measuring the irradiance during the Site Acceptance Test (Source: Reinhold Schmidt)]] Upon completion of the installation, the functionality and the performance of the system should be tested in the presence of the future user (producer). The testing includes a number of separate analyses. The first step is the acceptance test for the photovoltaic pumping system (PVP) which includes the PV generator, the mounting and tracking system (if part of the system), the controller and the water pump. These components are the “engine” of the SPIS, their performance is vital for the successful use of the irrigation system. |
− | Upon completion of the installation, the functionality and the performance of the system should be tested in the presence of the future user (producer). The testing includes a number of separate analyses. The first step is the acceptance test for the photovoltaic pumping system (PVP) which includes the PV generator, the mounting and tracking system (if part of the system), the controller and the water pump. These components are the “engine” of the SPIS, their performance is vital for the successful use of the irrigation system. | + | |
| | | |
| This acceptance test (also referred to as Site Acceptance Test, SAT) is the second level of material testing in view of quality management. Manufacturers of system components are obliged to run a Factory Acceptance Test (FAT) prior to releasing products to the supplier. Ideally, both levels of testing should be presented when evaluating an SPIS, but are not always readily available. | | This acceptance test (also referred to as Site Acceptance Test, SAT) is the second level of material testing in view of quality management. Manufacturers of system components are obliged to run a Factory Acceptance Test (FAT) prior to releasing products to the supplier. Ideally, both levels of testing should be presented when evaluating an SPIS, but are not always readily available. |
Line 22: |
Line 22: |
| {| style="width: 100%" cellspacing="1" cellpadding="1" border="0" | | {| style="width: 100%" cellspacing="1" cellpadding="1" border="0" |
| |- | | |- |
− | | style="background-color: rgb(225, 229, 205)" | | + | | style="background-color: rgb(225, 229, 205)" | |
| Measurement of solar irradiance --> Calculation of electrical power output--> Measurement and calculation of total pumping head --> Measurement of actual water flow ---> Comparison of measured and designed water flow | | Measurement of solar irradiance --> Calculation of electrical power output--> Measurement and calculation of total pumping head --> Measurement of actual water flow ---> Comparison of measured and designed water flow |
| + | |
| |} | | |} |
| | | |
Line 31: |
Line 32: |
| |- | | |- |
| | style="background-color: rgb(225, 229, 205)" | | | | style="background-color: rgb(225, 229, 205)" | |
− | '''Important''': Check on the tightness of seals and joints, screws and bolts. | + | '''Important''': Check on the tightness of seals and joints, screws and bolts. |
| | | |
| Check for signs of corrosion and cracked concrete foundations. | | Check for signs of corrosion and cracked concrete foundations. |
Line 38: |
Line 39: |
| | | |
| Record any deficiency and malfunction and discuss their amendment with the installer by the installer! | | Record any deficiency and malfunction and discuss their amendment with the installer by the installer! |
| + | |
| |} | | |} |
| | | |
− | The results of the acceptance test should be compared with the design performance of the PV pumping system. The '''[[:File:DESIGN_03-Pump_Sizing_Tool.xlsx|DESIGN – Pump Sizing Tool]]''' could be used to record the most important data and to compare it with the design values. The acceptance test protocol should be signed by the installer and the producer. | + | The results of the acceptance test should be compared with the design performance of the PV pumping system. The '''[[:File:DESIGN_–_Pump_Sizing_Tool.xlsx|DESIGN – Pump Sizing Tool]]''' could be used to record the most important data and to compare it with the design values. The acceptance test protocol should be signed by the installer and the producer. |
| | | |
− | The tool '''[[:File:SET_UP_01-PVP_Acceptance_Test.docx|SET UP – PVP Acceptance Test]]''' provides more details on the steps, required equipment and calculations involved in the acceptance test. | + | The tool '''[[:File:SET_UP_–_PVP_Acceptance_Test.docx|SET UP – PVP Acceptance Test]]''' provides more details on the steps, required equipment and calculations involved in the acceptance test. |
| | | |
| === '''<span style="color:#879637;">Outcome/Product</span>''' === | | === '''<span style="color:#879637;">Outcome/Product</span>''' === |
Line 49: |
Line 51: |
| *Comparison of actual performance to design performance; | | *Comparison of actual performance to design performance; |
| *Acceptance test protocol: | | *Acceptance test protocol: |
− | *'''[[:File:SET_UP_01-PVP_Acceptance_Test.docx|SET UP – PVP Acceptance Test]]'''. | + | *'''[[:File:SET_UP_–_PVP_Acceptance_Test.docx|SET UP – PVP Acceptance Test]]'''. |
| | | |
| === '''<span style="color:#879637;">Data Requirements</span>''' === | | === '''<span style="color:#879637;">Data Requirements</span>''' === |
Line 70: |
Line 72: |
| *A thorough check on the mechanical parts is recommended. | | *A thorough check on the mechanical parts is recommended. |
| | | |
− | | + | <br/>{{SPIS Reference}} |
− | {{SPIS Reference}} | + | |
Upon completion of the installation, the functionality and the performance of the system should be tested in the presence of the future user (producer). The testing includes a number of separate analyses. The first step is the acceptance test for the photovoltaic pumping system (PVP) which includes the PV generator, the mounting and tracking system (if part of the system), the controller and the water pump. These components are the “engine” of the SPIS, their performance is vital for the successful use of the irrigation system.
This acceptance test (also referred to as Site Acceptance Test, SAT) is the second level of material testing in view of quality management. Manufacturers of system components are obliged to run a Factory Acceptance Test (FAT) prior to releasing products to the supplier. Ideally, both levels of testing should be presented when evaluating an SPIS, but are not always readily available.
The different measurements should be carried-out within a short time interval under clear sky conditions. At least two ac-ceptance test runs are advisable, measuring at high irradiance (800 – 1,000 W/m2) and low irradiance levels (approx. 500 W/m2). The equipment for the test will be provided by the installer.
The results of the acceptance test should be compared with the design performance of the PV pumping system. The DESIGN – Pump Sizing Tool could be used to record the most important data and to compare it with the design values. The acceptance test protocol should be signed by the installer and the producer.