Line 1: |
Line 1: |
| + | [[Portal:Wind|► Back to Wind Portal]] |
| | | |
| = Overview = | | = Overview = |
| | | |
− | In contrast to [[Import_of_Energy_Products|imports]], local manufacturing of energy products can constitute a reasonable cost-efficient alternative that supports local value creation. | + | In contrast to [[Import of Energy Products|imports]], local manufacturing of energy products can constitute a reasonable cost-efficient alternative that supports local value creation. |
| | | |
| <br/> | | <br/> |
Line 19: |
Line 20: |
| = <span lang="EN-GB" style="font-size: 14pt; font-family: 'arial','sans-serif'">Further Information</span> = | | = <span lang="EN-GB" style="font-size: 14pt; font-family: 'arial','sans-serif'">Further Information</span> = |
| | | |
− | *[[Mini_/_Micro_Hydropower_Turbine_Manufacturing_in_Indonesia|Example: Mini & micro hydro power turbine manufacturing in Indonesia]] | + | *[[Mini / Micro Hydropower Turbine Manufacturing in Indonesia|Example: Mini & micro hydro power turbine manufacturing in Indonesia]] |
− | *[[Local_Manufacturing_of_Solar_Systems|Example: Local manufacturing of solar systems]] | + | *[[Local Manufacturing of Solar Systems|Example: Local manufacturing of solar systems]] |
− | *Local Production Systems of Wood Stoves: [[Enhancing_Production_of_Improved_Cookstoves_(ICS)|Enhancing production of ICS]] | + | *Local Production Systems of Wood Stoves: [[Enhancing Production of Improved Cookstoves (ICS)|Enhancing production of ICS]] |
| | | |
| <br/> | | <br/> |
Revision as of 15:35, 12 August 2014
► Back to Wind Portal
Overview
In contrast to imports, local manufacturing of energy products can constitute a reasonable cost-efficient alternative that supports local value creation.
Key Factors for Successful Local Production / Manufacturing[1]
- Relevant market: The demand of the relevant market should match the minimum size of one production unit. If a specific niche is big enough, the probability of success is higher. In Indonesia the niche was turbines for mini- and micro-hydro power, which has a high national demand and is not the core business of incumbents like Voith Hydro, Ossberger etc.
- Time factor: Establishing local production of hydro power components takes time (5-10 years). This is the biggest obstacle for projects which are only funded by EnDev and do not have a longer sectoral mandate like a focal area.
- Cluster: The production site / firm should be located within an industrial cluster, where it is easier to get qualified suppliers, employees etc. Multi-product firms are in a better position because they can compensate low demand with other product lines and transfer relevant knowledge to new technologies.
- No grants to the manufacturers. Better use (soft) loans or even better create trust for long-term investments like the German Feed-in Law did.
Further Information
References
- ↑ Outcome of a discussion during the GTZ mini-hydro power working group meeting in Nairobi, May 2009.