[edit]  Overview
 
Micro-Hydro Power (MHP) projects come along with a big variety of costs. Planning and developing a site brings a number of country, probably regional specific costs. Similar to that are costs for operation and maintenance. All different cost categories play a role for individual projects, while big difference between countries due to different framework condition might occur. A clear cost analysis upfront is highly recommended.
Cost Factors are Eventually:
- a locations feasibility check by respective personal
 - land/water ownership/usage
 - civil construction (canal, wear, intake, pipes, powerhouse)
 - electro-mechanical equipment (turbine, generator, load controller)
 - power grid (evtl. transformers, powerlines, house-cabeling, load limiters, meter installation, ...)
 - operation & maintenance (collecting tariffs, running and maintaining the assets)
 
Some remarks regarding costs:
- Land & water requirements are mostly small. But there may be interference with existing schemes (irrigation) or legal issues to be considered.
 - Order to delivery of electro-mechanical equipment may take half a year. Ensure to order in time.
 - Costs for power lines and household connections often require a substantial amount from the overall budged.
 - Any mhp scheme supplying a group of households has to install fixed procedures to cover operation & maintenance.
 - This includes the collection of tariffs from each user.
 
[edit]  Example: Micro-Hydro Power (MHP) Costs in Rwanda
 
-> Rwanda Energy Situation
[edit]  Further Information 
[edit]  References