Line 1: |
Line 1: |
| | | |
− | = Overview and General Information<br/> = | + | = Overview<br/> = |
| | | |
− | '''<u>Location of the site:</u>'''
| + | Name of the site: El Plan<br/>Turbine Type: Pelton Country: Nicaragua (GPS Coordinates: ?)<br/> |
− | *<u>Country</u>: Nicaragua
| + | |
− | *<u>District</u>:
| + | |
− | *<u>River</u>:
| + | |
− | *<u>GPS Coordinates</u>:
| + | |
| | | |
| + | <br/>'''Start of Construction:''' December 2011<br/>'''Date of Commissioning:''' June 2012<br/>'''Ownership / Operation Model:''' Privately owned<br/>'''Tariff structure:''' Not applicable<br/> |
| | | |
| + | = Operation Data<br/> = |
| | | |
| + | = Technical Information<br/> = |
| | | |
− | = Further Information<br/> = | + | == Civil Works<br/> == |
| | | |
− | '''Start of Construction:''' December 2011<br/>
| + | == Electromechanical Equipment<br/> == |
− | '''Date of Commissioning:''' June 2012<br/>
| + | |
− | '''Ownership / Operation Model:''' Privately owned<br/>
| + | |
− | '''Tariff structure:''' Not applicable<br/>
| + | |
− | '''Turbine:''' Pelton<br/>
| + | |
− | '''Generator:''' Modified direct drive motor, 3 phase, 20 V, 150 W (approximately)<br/>
| + | |
− | | + | |
− | | + | |
− | = Ressources - Codicions<br/> = | + | |
− | | + | |
− | | + | |
− | = Civil Works<br/> =
| + | |
− | | + | |
− | | + | |
− | = Electromechanical Equipment<br/> = | + | |
− | | + | |
− | | + | |
− | = Electrical Transmission<br/> =
| + | |
| | | |
| + | == Electrical Transmission<br/> == |
| | | |
| = Economic Information<br/> = | | = Economic Information<br/> = |
Revision as of 21:48, 26 March 2014
Overview
Name of the site: El Plan
Turbine Type: Pelton Country: Nicaragua (GPS Coordinates: ?)
Start of Construction: December 2011
Date of Commissioning: June 2012
Ownership / Operation Model: Privately owned
Tariff structure: Not applicable
Operation Data
Technical Information
Civil Works
Electromechanical Equipment
Electrical Transmission
Economic Information