  Overview
 
Location of the site:
- Country: Germany
 - District: Baden-Württemberg
 - River: Schanzbach
 - GPS Coordinates: 47º55’40.5’’N 7º55’31.2’’E
 
This pico pelton turbine is part of a hybrid system which supplies electricity to the Häusleberg Organic Farm. For more information please go to the project website: sites.google.com/site/haeusleberg/
  Further Information - Project
 
Start of Construction: December 2011
Date of Commissioning: June 2012
Ownership / Operation Model: Privately owned
Tariff structure: Not applicable
Turbine: Pelton
Generator: Modified direct drive motor, 3 phase, 20 V, 150 W (approximately)
   A view over the Häusleberg organic farm  
 | 
| 
  
 
 | 
    Side view of the installed turbine atop the wooden framed drainage barrel.  
 | 
    Top view of the installed turbine atop the wooden framed drainage barrel.  
 | 
  
 | 
  
 | 
    The turbine from below showing the pelton runner at the nozzle mounting bracket.  
 | 
    The stator of the direct drive motor during modifications for the 12 V hybrid system.  
 | 
  
 | 
  
 | 
    Nozzle alignment test.  
 | 
 | 
  
 | 
 | 