  What use can a hydropower installation satisfy?  
- Direct drive of machinery 
 - Electricity production for local use 
 - Electricity feed into grid for revenue
 
  How many people can be supplied? 
- Available share per household (hh) depends on local hydro potential and type of use (lighting, TV, machinery, ...) 
 - Required power for lighting depends on no. and type of lamps used (3 - 5 Watt energy saving lamps are existing)
 - Machinery needs usually several kW (often machinery's power is given in HP (metrical Horsepower) 10 HP = 7.36 kW)
A motors starting power can be 50% higher than its regularly stated power. There are technical possibilities to address these (soft start).
 - Electrical heating requires very high power. E.g. has a typical water heater ~ 3 kW. Within an isolated grid, electrical heating / cooking / oven  is usually not practicable. Hot water can be produced centrally from the ballast load.
 - Electrical cooling is possible.  
 - Electrical fan ~ 200 Watt.
 - Radio / DVD ~ 10 W / 2 W
 - Water pump  ~ 1 kW
 - TV 50 -150 W (depending on type and size)
 
What are typical difficulties
- financial coverage
 - remote location
 - specific conditions
 - uncertain outcome
 
- Price range: depends on size of potential site, ranges from 2000 - 5000 USD/kW 
 - Material needed: Turbine, generator, controller come from a specialist   
 - Suitable geographic area: usual hilly and all year round water flow, also irrigation canals can have good hydropower potential 
 - Required competencies: Experience in mhp feasibility for pre-study and planning, patience in cooperation with the local entities
 - How Long does it take: Ideally flow measurements should be taken over several years to ensure safe data. A must is the measurement of the minimal flow during dry season. From there on a mhp plant can be installed within one year. Accessibility of remote location, delivery times for turbine and generator and social setup usually take longer than estimated. 
 
 